RDT have recently completed the design, supply and installation of a MRF in Lancashire to process 100,000 tonnes per annum of plastic, glass, steel and aluminium as well as loose loading and baling of source separated OCC & paper. The initial designs were completed in 2005 and detailed engineering was finished late in 2008.
A team of RDT engineers traveled to England for 5 months to manage the successful installation of the plant, working with local suppliers and installation sub contractors.RDT won the exporter of the year award from the Australian British Chamber of Commerce in 2008 for the design and construction of this facility.
Project Duration: 20 weeks
Major Equipment utilized in the new MRF: